TOWN / AREA
|
CLIENT
|
CONSULTANTS / REFERENCES
|
CONTACT PERSON
|
DESCRIPTION OF CONTRACT
|
VALUE INCL. VAT
|
CIDB
GRADING
|
DATE OF APPOINTMENT
|
ANTICIPATED
COMPLETION DATE
|
Libode
|
OR Tambo Municipality
|
Arcuss Gibb
|
Mr N Mkhwanazi 031 267 8560
|
Libode Bulk Water Supply Pipeline: Gravity Main from existing 3ML Reservoir to Booster Pump
|
R49,6 mill
|
8CE
|
June 2012
|
June 2013
|
Butterworth
|
Amathole District Municipality
|
Sigodi Marah Martin Management Support
|
Mr. Sellu Waden 071 960 9229
|
Ibika-Centane Water Supply Phase 2A: Bulk and Reticulation.
|
R28,7 mill
|
7 CE
|
Nov 2012
|
June 2013
|
Mthatha
|
King Sabata Dalindyebo Municipality
|
Arcuss Gibb
|
Mr. Bright Faya
031 267 8560 /
047 531 0164
|
Construction of Siqikini Extension Access Road
|
R15,1 mill
|
7 CE
|
Nov 2012
|
Aug 2013
|
QwaQwa
|
Thabo Mofutsanyana District Municipality
|
Infrastructure and Transport Department
|
Mr. M.B. Mphahlele 058 713 4485
|
Gravel Road Upgrade to Brick Block Paving in Bolata Village Phase 2
|
R4,6 mill
|
4 CE
|
May 2013
|
Sept 2013
|
Port Alfred
|
Amatola Water - Amanzi
|
Aurecon Group
|
Mr. Steve Landolt 043 721 0900
|
Ndlambe Bulk Water Supply Schem: Quick Wins: Ground Water Supply from the Central Belt for Port Alfred: Civil Works
|
R28,6 mill
|
6 CE
|
Feb 2013
|
Sept 2013
|
Harrismith
|
Maluti-A-Phofung Municipality
|
Kgatho Project Management
|
Mr. B. Beth
058 303 1236
|
Construction of a New 4ML Ground Reservoir for Makholokweng Area
|
R12,4 mill
|
6 CE
|
April 2013
|
Nov 2013
|
Harrismith
|
Department of Rural Development and Land Reform – Free State
|
Dikgobo Consulting Engineers
|
Mr. M. Mngadi
011 656 4075
|
Construction of Bridge and Road Paving in Diyatalawa - Harrismith
|
R21,9 mill
|
7 CE
|
April 2013
|
Nov 2013
|
Rustenburg
|
Rustenburg Local Municipality
|
Bigen Africa Engineers
|
Mr. Leon Boschoff
012 842 8730
|
Construction of the Rustenburg Rapid Transport(RRT) North East Corridor – Contract B
|
R261 mill
|
8 CE PE / 9CE
|
May 2013
|
Jan 2015
|